Precedence diagram method

The precedence diagram method (PDM) is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes, referred to as nodes, to represent activities and connects them with arrows that show the dependencies. It is also called the activity-on-node (AON) method.

Key elements include determining predecessors and defining attributes such as

Slack/Float: Determines the duration of activity delay that the project can tolerate before the project comes in late. The difference between the earliest and the latest start time. i.e. Slack = last start date - early start day or Slack = last finish time - early finish time.

Any activities which have a slack of 0, they are on the critical path.

solving the PDM, with: BS is an early start date. BM is a late start date. KS is an early finish date. KM is a late finish date.

See also

External links

This article is issued from Wikipedia - version of the 6/7/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.