Putnam Bridge (New York City)

Putnam Bridge
Coordinates 40°49′55.75″N 73°56′3.56″W / 40.8321528°N 73.9343222°W / 40.8321528; -73.9343222Coordinates: 40°49′55.75″N 73°56′3.56″W / 40.8321528°N 73.9343222°W / 40.8321528; -73.9343222
Carries Putnam Division (1881-1918), 9th Avenue El (1918-1940), Polo Grounds Shuttle (1940-1958)
Crosses Harlem River
Locale Manhattan and the Bronx, in New York City
Characteristics
Design Swing bridge
Total length 1,004.4 feet (306.1 m)
Width 40 feet (12.19 m) including walkways
Longest span 297 ft 8 38 in (90.74 m)
Clearance below 28 feet (8.53 m)
History
Opened May 1, 1881
Closed August 31, 1958

Putnam Bridge was a swing bridge that spanned the Harlem River and the adjacent tracks of the New York, New Haven & Hartford Railroad in New York City, connecting the boroughs of Manhattan and the Bronx near the current location of Yankee Stadium. It carried two tracks of the New York & Putnam Railroad, and later the 9th Avenue elevated line of the IRT, as well as two pedestrian walkways outside the superstructure.

The bridge opened to rail and pedestrian traffic on May 1, 1881. As with the other Harlem River swing bridges, the bridge was designed by Chief Engineer Alfred Pancoast Boller; the contractors were Clarke, Reeves & Co., and Smith, Ripley & Co. The bridge's total length was 1,004.4 feet (306.1 m), comprising a main span of 300 feet (91 m) (the largest double-track draw span in the world at the time of construction), two identical deck truss side spans of 100 feet (30 m) each, and four approach spans on either side.[1] When closed, the bridge provided 28 feet (8.5 m) of vertical clearance, and when opened, two shipping channels of 124 feet (38 m) and 123 feet (37 m) in the east and west channels respectively.[2]

The Putnam Bridge was built by the New York City & Northern Railroad, a predecessor of the NY&P, and operated by its subsidiary, the West Side & Yonkers Railway (not to be confused with the West Side and Yonkers Patent Railway, the original operator of the 9th Avenue line). The location for the bridge was formally approved by the Board of Parks Commissioners on January 7, 1880.[3] Construction was authorized by the Board of Rapid Transit Commissioners on February 18, 1880,[4] was underway by April of that year,[5] and completed April 28, 1881; train service began running on the following Sunday, May 1, 1881.[6] The construction was marred by an accident on November 26, 1880, when a truss that was being moved into position flipped over unexpectedly, knocked a second truss loose, and caused both to fall through the scaffolding, killing one laborer and injuring four others,[7] but otherwise proceeded without notable incident.

Service

The NY&P and its successor, the NYC&HR's Putnam Division, continued to run trains over the bridge until January 6, 1918, at which time service was cut back to a new terminal at Sedgwick Avenue, on the Hudson Division's right of way in the Bronx, and the northward-curving structure connecting the east end of the bridge to the Hudson Division was demolished. The IRT, which by then had taken over operation of the 9th Avenue El from the Manhattan Railway, reconfigured the 155th Street terminal to allow elevated trains direct access to the bridge, and on the Bronx side of the river constructed a new right-of-way, partially elevated and partially in tunnel, eastward from the bridge to a connection with the new Jerome Avenue elevated line at 162nd Street. Through service over this new line to the 167th Street station was inaugurated July 1 of that year, and extended to the northern terminus at Woodlawn by January 2, 1919.

Train service on the 9th Avenue El south of 155th Street was discontinued June 12, 1940, on the occasion of the City of New York assuming operation of the IRT; nevertheless, the segment crossing the bridge continued to be operated between 155th Street in Manhattan and 167th Street in the Bronx, as a shuttle serving the Polo Grounds. However, the New York Giants baseball team was moved from the Polo Grounds to San Francisco after the 1957 season, and the Putnam Division ceased running passenger service on May 29, 1958. These two events reduced ridership to the extent that it no longer made economic sense to continue running the shuttle, and it was discontinued August 31, 1958. The bridge's extreme narrowness of 26 feet (7.9 m) between the centers of the trusses,[8] combined with the presence of the Macombs Dam Bridge only a few hundred feet to the south, made it impractical and unnecessary to convert to a roadway bridge, and it was removed in 1960.

References

Notes
  1. "Toward Boston Via Manhattan Elevated", Trains Magazine, December 1947
  2. U.S. Coast & Geodetic Survey, Chart #274, revision of 7/14/1958
  3. "A Bridge Across The Harlem River", New York Times, January 8, 1880
  4. "City & Suburban News", New York Times, February 19, 1880
  5. "City & Suburban News", New York Times, April 10, 1880
  6. "Train Through To Brewster's", New York Times, April 29, 1881
  7. "Heavy Iron Trusses Fall", New York Times, November 27, 1880
  8. Phoenix Bridge Company. Album of designs of the Phœnix Bridge Company : successors to Clarke, Reeves & Co., Phœnixville Bridge Works. J. B. Lippincott & Co., 1885. p.31
This article is issued from Wikipedia - version of the 12/3/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.